When will your home be part of the programme?

Many residents have already had new kitchens and bathrooms. The refurbishment work covers inside homes and the external fabric of buildings.

 Internals

On the internals programme 439 properties have had a new kitchen and bathroom and there are 150 remaining to be completed.

External Works Programme

The table below shows the provisional start dates for work to the blocks being refurbished this year.  While we will make every effort to stick to the dates shown there will inevitably be some issues which mean we have to change either the start or finish dates.  For example, we had move Sligo House to later in the programme as during our pre-commencement surveys we discovered some problems with the existing roof which will now have to be replaced rather than just repaired as originally expected.  We will give you as much notice as possible if we have make changes and you will receive letters prior to any work starting explaining what we will be doing to your block or house and how this will affect you.

We have shown which blocks have work being done to their lifts as we understand this may affect those of you living on the upper floors of multi-storey blocks.  If you have any concerns about the refurbishment work being completed please contact your RLO.

Block/Road Projected Start Date Projected Completion Date Lift Works
Anson House Mar-12 Sep-12 Repair/Upgrade
Arabian House Feb-12 Jul-12 Repair/Upgrade
Azov House May-12 Sep-12 Repair/Upgrade
Broadford House Aug-12 Nov-12  
Cambay House Feb-12 Jun-12  
Coral House Mar-12 Jul-12  
Cromarty House Oct-12 Feb-13 Repair/Upgrade
Duckett Street Mar-12 Mar-12  
Durham Row May-12 Jul-12  
Emmott Close May-12 Dec-12 Full Replacement
Ernest Street Mar-12 Apr-12  
Galway House Aug-12 Nov-12 Full Replacement
Greenland House Feb-12 Jul-12 Repair/Upgrade
Ionian House Jan-12 Apr-12  
James House Apr-12 Nov-12  
Lorne House Oct-12 Feb-13 Repair/Upgrade
Milrood House Oct-12 Jan-13  
Moray House Jun-12 Oct-12 Repair/Upgrade
Morecambe Close May-12 Aug-12  
Panama House Aug-12 Dec-12  
Pegasus House Apr-12 Aug-12  
Pevensey House Sep-12 Dec-12  
Rectory Square Flats Jul-12 Nov-12  
Rectory Square Houses Jul-12 Aug-12  
Sandalwood House May-12 Nov-12 Full Replacement
Shandy Street Mar-12 May-12  
Sligo House May-12 Sep-12  
Solent House Sep-12 Jan-13 Repair/Upgrade
Stepney Green May-12 May-12  
Timor House Jan-12 May-12  
Weddell House May-12 Sep-12  
White Horse Lane Feb-12 May-12  